ALTEN China has established a strong collaboration with a leading global telecommunications company, offering end-to-end engineering solutions for automated testing and product verification. ALTEN China plays a key role in ensuring the quality and on-time delivery of the client’s base stations through thorough testing, tool development, and R&D collaboration. These contributions are vital to helping the client meet stringent product standards prior to mass production, ensuring the delivery of high-quality telecommunications equipment.

 

Challenges

  • The telecom industry faces several key challenges, particularly in ensuring the quality and reliability of products before mass production:
  • Complex Testing Requirements: The client’s base stations require a highly specialized testing environment, including both hardware and software components, to ensure they meet stringent quality standards.
  • Automated Testing Development: The need to develop automated testing tools that can efficiently test various product modules (TRX, PA, RRH, aging) while maintaining accuracy and consistency.
  • Quality Assurance: Ensuring that every base station passes rigorous RF and functional testing to guarantee reliable performance in diverse network environments.
  • Timely Issue Resolution: Identifying and fixing product issues early in the development cycle to avoid delays in mass production and ensure products meet client specifications.
  • The client required a reliable partner with expertise in automated testing, R&D support, and quality verification to ensure their products met high standards and could be delivered on time.

 

Solutions

ALTEN China assembled a specialized engineering team to provide a wide range of testing and R&D services, ensuring seamless product verification and quality control:

1. Testing Environment Preparation & Verification

  • Test Case Execution: Implemented testing cases based on detailed R&D manuals, collected and analyzed results to identify product issues.
  • Issue Reporting & Resolution: Coordinated with the R&D team to resolve identified issues, ensuring that all problems were addressed before moving to the next phase of mass production.

2. Automated Testing Tool Development

  • Tool Development: Designed and developed automated testing tools to streamline the testing process and improve efficiency, reducing the time needed for manual tests while ensuring accuracy.
  • Coding & Tooling: Led the coding of all F-ASB projects, developed automated testing scripts, and validated tools to ensure the base stations met all production and functionality standards.

3. Test Case Implementation & Issue Resolution

  • Test Case Execution: Implemented testing cases based on detailed R&D manuals, collected and analyzed results to identify product issues.
  • Issue Reporting & Resolution: Coordinated with the R&D team to resolve identified issues, ensuring that all problems were addressed before moving to the next phase of mass production.

4. Hardware Function Verification & Database Maintenance

  • HW Verification: Conducted hardware function verification, including the testing of DFBA (Design for Best Availability) and DFFA (Design for First Failure Analysis) to ensure the robustness of hardware components.
  • Database Management: Managed the debugging and maintenance of production databases, ensuring that all test data was properly tracked and issues were resolved in a timely manner.

 

Outcomes

Through continuous collaboration, ALTEN China delivered significant value to the client, ensuring high-quality product verification and timely production:

  • Improved Product Quality: Automated testing tools and rigorous testing procedures contributed to high-quality, reliable base stations that met the client’s strict performance standards.
  • Faster Issue Detection & Resolution: The implementation of automated testing reduced the time needed to identify and resolve product issues, ensuring a smoother path to mass production.
  • Optimized Production Timelines: Comprehensive testing and tool development helped streamline the production process, ensuring timely delivery and high-quality products for the client.
  • Enhanced R&D Collaboration: Close coordination with the R&D team helped resolve issues early in the process, minimizing delays and improving overall product development efficiency.